05 July 2007

Water

The dam had about 200mm of water in it on Friday. By Wednesday it was completely full, about 1700mm deep. The rainfall during that time was only just over 50mm.


Lots of water is still standing in the paddocks; not very deep though.

Start of the roof


The roof will be constructed using trusses. They will be pitched off the verandahs. The beams for the verandah are in place. The internal walls are being constructed today and tomorow, and the trusses are due to be ready in the next week.

24 May 2007

Rammed earth wall finished

From right to left: kitchen, pantry, laundry and bathroom 2.

Through laundry door to dining area.

Back from house from next to garage.

Front (above) and side (below) of house from a distance.


From office into bathroom 1 and then bedroom 1.

From dining to laundry, bathroom 2 and bedroom 3.

From bedroom 1 to office.

Entry.

10 May 2007

Progress - at dusk

Entry Wall

Looking across the lounge to the main bedroom.

View from below concrete pad level.


Alcove in the wall of the family room.

Alcove in wall of passage between office and bedroom.


Bobcat in the bathroom.


Bathroom and toilet windows

29 April 2007

More walls going up

View of the top of the bathroom and bedroom walls.

Across the pad from garage to bedroom 1 (left) and the study/office (right).

The storeroom and garage walls.

View from higher up.

20 April 2007

First walls

The first section of rammed earth wall is complete - north west corner of the garage.

15 April 2007

The start of the rammed earth walls

The mixing pad. Limestone, gravel and cement (cream and grey) is mixed by a bobcat.

The formwork for the first wall.

11 April 2007

Ready for the walls

The completed concrete floor.

10 April 2007

Pouring the slab


The concrete pump and concreters at work.

The completed slab at night after I had watered it.


05 April 2007

Footings


Footings in the early morning fog.

28 March 2007

Two sand pads

The pad is rather large (but far smaller than Phil and Janet's) so I had to stand well back!

The pad for the chook pen.

The job is done

Allan finishing off the pad.



27 March 2007

More sand

Early Tuesday morning, with less than 1/4 done. Four trucks drove back and forth all day from the WA Limestone sandpit on Millar Road.

End of tuesday. The sand pad is 3/4 completed.

26 March 2007

Here comes the sand


The trucks of sand arriving at 6.15am. Allan Butts directing them.

25 March 2007

The start


The site for the house.

01 January 2007



More sunsets over the dam.

01 December 2006

The vegies are growing well.

Dam level is falling. First picture of the 'new' front gates on these pages.